CONSTRUCTION PROJECT TRACKER
BLO Daytona
Level 3 critical-path schedule · August 13–December 1, 2026
Overall completion0%
Project status is maintained by Build Studio.
KEY INSPECTIONS
Control points
SCHEDULE BASIS
Protect December 1
01
Inspection turnaround
Plan assumes next-business-day turnaround and no failed inspections.
02
Combined inspections
Exact inspection codes and grouping remain subject to local AHJ confirmation.
03
Material readiness
Long-lead fixtures and trade material must remain available to the field.
04
Utilities and weather
Target assumes no significant utility or weather delay.